New Jersey, October 20, 2025
A dispute over offshore vessel regulations threatens to delay the Empire Wind project off New Jersey’s coast. Environmental groups and developers are conflicting over guidelines, which could impact the timelines for renewable energy deployment. Federal oversight is seen as critical to resolving the standoff and ensuring that clean power goals are met. The situation highlights the ongoing tension between environmental concerns and the urgent need for sustainable energy development.
New Jersey
New Jersey – The Empire Wind project, an offshore wind farm located approximately 17 miles east of Long Branch, New Jersey, is facing considerable construction challenges that may delay its advancement. Developed by Equinor ASA, the project aims to deliver renewable energy to the region but is currently hindered by disputes over offshore vessel availability and regulatory approvals.
Offshore Vessel Dispute
In October 2025, Maersk Offshore Wind terminated a $475 million contract with Singapore-based shipbuilder Seatrium Energy International, which was tasked with constructing a nearly completed offshore wind turbine installation vessel for the Empire Wind project. Maersk cited construction delays and related issues as the reason for the contract termination. In response, Seatrium announced it is exploring its options, including potential legal action and alternative uses for the vessel. This situation adds to the broader challenges facing the U.S. offshore wind sector, which has encountered opposition, including a recent halt work order on the Empire Wind project. Equinor has acknowledged the issue and is assessing potential next steps.
Regulatory Challenges
In April 2025, the U.S. Department of the Interior issued a halt work order on the Empire Wind project, citing concerns regarding the project’s approvals and potential environmental impacts. Although the order was lifted in May 2025, allowing construction to resume, environmental and fisheries groups have initiated lawsuits aimed at halting the project, arguing it poses risks to marine life, fishing grounds, and coastal economies. These legal actions highlight the ongoing tensions between renewable energy development and stakeholders in the environmental and fishing industries.
Background Context
The Empire Wind project is designed to span approximately 79,350 acres in the New York Bight, with a combined potential capacity of over 2 gigawatts across two phases—Empire Wind 1 and Empire Wind 2. Despite obtaining the necessary federal and state permits and commencing construction in 2024, the project continues to face numerous challenges, including regulatory scrutiny and opposition from environmental and fishing industry groups. These developments underscore the complexities involved in advancing large-scale renewable energy projects in the United States.
Frequently Asked Questions (FAQ)
What is the Empire Wind project?
The Empire Wind project is a planned offshore wind farm located approximately 17 miles east of Long Branch, New Jersey. Developed by Equinor ASA, it aims to provide renewable energy to the region with a combined potential capacity of over 2 gigawatts across two phases—Empire Wind 1 and Empire Wind 2.
What challenges is the Empire Wind project currently facing?
The project is encountering significant construction challenges, including a dispute over offshore vessel availability. In October 2025, Maersk Offshore Wind terminated a $475 million contract with Seatrium Energy International for the construction of a nearly completed offshore wind turbine installation vessel intended for the project. Additionally, environmental and fisheries groups have filed lawsuits seeking to halt the project, citing potential risks to marine life, fishing grounds, and coastal economies.
What is the current status of the Empire Wind project?
As of October 2025, the Empire Wind project is facing significant construction challenges that may delay its progress. The project is currently under construction, but disputes over offshore vessel availability and ongoing legal challenges from environmental and fisheries groups are impacting its timeline.
What is the significance of the Empire Wind project?
The Empire Wind project is significant as it represents a major step in advancing offshore wind energy in the United States, particularly in the New York Bight area. If completed, it has the potential to provide renewable energy to the region, contributing to the nation’s clean energy goals and reducing reliance on fossil fuels.
How are environmental and fisheries groups involved in the Empire Wind project?
Environmental and fisheries groups have been actively involved in the Empire Wind project by filing lawsuits seeking to halt its construction. They argue that the project poses risks to marine life, fishing grounds, and coastal economies, and have called for a halt to the project to address these concerns.
What is the current status of the lawsuits against the Empire Wind project?
As of October 2025, environmental and fisheries groups have filed lawsuits seeking to halt the Empire Wind project, citing potential risks to marine life, fishing grounds, and coastal economies. These legal actions are ongoing, and their outcomes may impact the project’s future development.
FAQ Schema in JSON-LD Format
{ "@context": "https://schema.org", "@type": "FAQPage", "mainEntity": [ { "@type": "Question", "name": "What is the Empire Wind project?", "acceptedAnswer": { "@type": "Answer", "text": "The Empire Wind project is a planned offshore wind farm located approximately 17 miles east of Long Branch, New Jersey. Developed by Equinor ASA, it aims to provide renewable energy to the region with a combined potential capacity of over 2 gigawatts across two phases—Empire Wind 1 and Empire Wind 2." } }, { "@type": "Question", "name": "What challenges is the Empire Wind project currently facing?", "acceptedAnswer": { "@type": "Answer", "text": "The project is encountering significant construction challenges, including a dispute over offshore vessel availability. In October 2025, Maersk Offshore Wind terminated a $475 million contract with Seatrium Energy International for the construction of a nearly completed offshore wind turbine installation vessel intended for the project. Additionally, environmental and fisheries groups have filed lawsuits seeking to halt the project, citing potential risks to marine life, fishing grounds, and coastal economies." } }, { "@type": "Question", "name": "What is the current status of the Empire Wind project?", "acceptedAnswer": { "@type": "Answer", "text": "As of October 2025, the Empire Wind project is facing significant construction challenges that may delay its progress. The project is currently under construction, but disputes over offshore vessel availability and ongoing legal challenges from environmental and fisheries groups are impacting its timeline." } }, { "@type": "Question", "name": "What is the significance of the Empire Wind project?", "acceptedAnswer": { "@type": "Answer", "text": "The Empire Wind project is significant as it represents a major step in advancing offshore wind energy in the United States, particularly in the New York Bight area. If completed, it has the potential to provide renewable energy to the region, contributing to the nation's clean energy goals and reducing reliance on fossil fuels." } }, { "@type": "Question", "name": "How are environmental and fisheries groups involved in the Empire Wind project?", "acceptedAnswer": { "@type": "Answer", "text": "Environmental and fisheries groups have been actively involved in the Empire Wind project by filing lawsuits seeking to halt its construction. They argue that the project poses risks to marine life, fishing grounds, and coastal economies, and have called for a halt to the project to address these concerns." } }, { "@type": "Question", "name": "What is the current status of the lawsuits against the Empire Wind project?", "acceptedAnswer": { "@type": "Answer", "text": "As of October 2025, environmental and fisheries groups have filed lawsuits seeking to halt the Empire Wind project, citing potential risks to marine life, fishing grounds, and coastal economies. These legal actions are ongoing, and their outcomes may impact the project's future development." } } ] }
Key Features of the Empire Wind Project
Feature | Details |
---|---|
Location | Approximately 17 miles east of Long Branch, New Jersey |
Developer | Equinor ASA |
Project Phases | Empire Wind 1 and Empire Wind 2 |
Combined Potential Capacity | Over 2 gigawatts |
Current Status | Facing construction challenges and legal disputes |
Deeper Dive: News & Info About This Topic
HERE Resources

Author: NEW JERSEY STAFF WRITER
The NEW JERSEY STAFF WRITER represents the experienced team at constructionnjnews.com, your go-to source for actionable local news and information in New Jersey and beyond. Specializing in "news you can use," we cover essential topics like product reviews for personal and business needs, local business directories, politics, real estate trends, neighborhood insights, and state news affecting the area—with deep expertise drawn from years of dedicated reporting and strong community input, including local press releases and business updates. We deliver top reporting on high-value events such as the New Jersey Build Expo, major infrastructure projects, and advancements in construction technology showcases. Our coverage extends to key organizations like the Associated Builders and Contractors of New Jersey and the New Jersey Builders Association, plus leading businesses in construction and legal services that power the local economy such as CMiC Global and Gibbons P.C. As part of the broader network, including constructioncanews.com, constructionnynews.com, and constructiontxnews.com, we provide comprehensive, credible insights into the dynamic construction landscape across multiple states.